Case Study: Public Infrastructure

Pune Government BIM Infrastructure: FDA, Pali, Sarthi & GSDA

Delivering full LOD 350 Building Information Models and cross-disciplinary clash resolution for landmark state administrative facilities in Maharashtra.

Executive Summary

Public infrastructure projects in Maharashtra require strict compliance with state authority standards while facing tight budget allocations and uncompromising public audit scrutiny. Anuman was engaged to execute end-to-end 3D Building Information Modeling (BIM) and spatial coordination across several major state government institutions in Pune, including:

  • FDA (Food and Drug Administration) Pune: Specialized lab facilities and administrative wings with complex HVAC and cleanroom ducting.
  • Pali Language Research Institute: Institutional academic architecture with distinct acoustic and structural spans.
  • SARTHI (Chhatrapati Shahu Maharaj Research Training & Human Development Institute): Multi-story training auditoriums, hosteling, and administrative offices.
  • GSDA (Ground Water Surveys & Development Agency): Geological testing facilities and regional data repository headquarters.

The Challenge: High MEP Density & Risk of Site Stoppages

Traditional 2D drawings from separate architectural, structural, and MEP consultants contained numerous spatial contradictions. HVAC chill lines collided with main structural columns, and drainage gradients cut through electrical riser shafts. If left unaddressed until on-site casting, rectifying these conflicts would have triggered multi-month project delays and significant budget overruns.

Critical Risk: In government infrastructure contracts, post-tender scope modifications and structural rework cause dispute arbitration and severe contractor penalty deductions.

The Execution Strategy

Anuman deployed a structured 3-phase BIM coordination workflow:

1

LOD 350 Parametric Discipline Modeling

Created accurate 3D parametric representations of structural concrete frameworks, architectural envelopes, and all mechanical, electrical, and plumbing (MEP) systems based on tender design blueprints.

2

Hard & Soft Clash Matrix Analysis

Ran comprehensive interference checks in Navisworks, identifying over 140 geometric clashes prior to site execution. Rerouted ducting and adjusted sleeve placements in agreement with the structural consultant.

3

Precise Material Takeoff & BOQ Validation

Extracted verified rebar, concrete volume, and ducting quantities directly from the BIM database, arming the contractor with pinpoint procurement schedules.

Quantified Outcomes & Verified Impact

0%
Improvement in Material Efficiency
Reduction in scrap rebar and concrete wastage
0+
Clashes Resolved Pre-Execution
Zero critical MEP stoppages during slab pouring
Next Project